Progress report for 14th land readjustment project

  • Date: 2019-03-19
  • Issued by: Land Administration Bureau

1. The 14th administrative are a belongs to Beitun District of Taichung City. The project area looks like a three-sidedㄇ. At its east side is Touzhang (頭張) of Tanzi Township, in the middle are the 11th Redevelopment Zone and Sizhangli (四張犁) of Taichung City, on the west side is Xitun Shuinan region, and on the north side is the80-meter-wide Huanzhong Road(環中路). The total area for the project is approximately 403.39 hectares, and this 14th land readjustment zone is named Meihe Chuang (美和庄), which is approved by the Mayor.
2. Compensation to the land owners is currently under way. The construction progress of each Work Area is reported as follows:
(1) Public facilitiesfor the 1st Work Area is currently under construction.
(2) For the 2nd and 3rd Work Areas, compensation lists for above-ground objects were displayed for 30 days between August 25, 2011and September26, 2011.Compensation for buildings and crops was paid between April 24 and 26, 2012. Incentives for voluntary building removal were paid betweenSeptember 25 and 27, 2012. Compensation lists for above-ground objects (re-estimated) were displayed for 30 days between November 28, 2012 and December 28, 2012.
(3) For the 4th Work Area, compensation lists for above-ground objects(re-estimated 2)were displayed for 30days between July 16, 2012and August 15, 2012.Re-estimated compensation was paid on September3, 2012.Contract awarding for the project was made on May 18, 2012.Ground breaking ceremony was held on August 14, 2012.Project Lot B commenced construction on October 15, 2012 whileProject Lot Abeganon November 1, 2012.the 1st start the applications. Compensation lists for above-ground objects (re-estimated 3) were displayed for 30 days between November 28, 2012 and December 28, 2012.
(4) For the 5th Work Area, compensation lists for above-ground objects (re-estimated 2) were displayed for 30days between July 24 and August 23, 2012. Re-estimated compensation was paid on September 3, 2012.Contract for Project Lot B was awarded on July 13, 2012 while the awarding of Project Lot A was given on August 27, 2012. Ground breaking ceremony for the project was held on December 14, 2012.
(5) For the 6th Work Area, compensation lists for above-ground objects were displayed for 30 days between August 25, 2011 and September 26, 2011, while the compensation lists for above-ground objects (re-estimated) were displayed for 30days between November 28, 2012 and December 28, 2012.